Walnut kitchen, garden room addition and a new primary suite for a 1956 house

Clarendon Hills, 2026

Sample project

A couple with two teenagers wanted the kitchen to face the yard. We designed a small addition, moved the kitchen into it and rebuilt the primary suite while the walls were open.

Service
Design-build
Scope
Kitchen, 280 sq ft rear addition, primary bedroom and bath
Schedule
12 weeks of design, 5 for the permit, 22 of construction
Finished
August 2026
White island with four oak stools in front of floor-to-ceiling walnut cabinets and a brass pendant

The brief

The 1956 house had its kitchen in the middle, with no window over the sink and the yard visible only from a back bedroom.

The owners asked for three things in their first email: see the yard while cooking, seat four at the island, and stop carrying laundry up and down the basement stairs.

Kitchen with a wall of walnut cabinets, a white island with four wood stools and a dining table in front
The tall walnut wall holds the refrigerator, the pantry and the ovens.

What we had to work around

The rear setback left 14 feet of depth for the addition, and the lot slopes away from the house.

A 1950s gas line ran through the old kitchen wall. The family stayed in the house the whole time, so the old kitchen had to keep working until the new one was ready.

Carpenter marking a sheet of plywood with a pencil and a yellow tape measure
Week 9 of construction: cabinet bases set out on site before the walnut doors arrived.
Round dining table with four white upholstered chairs beside sliding doors to a deck
The garden room: two sliding doors to a new deck.

What we decided

Everything tall went on one wall: refrigerator, pantry, two ovens and a broom closet behind walnut veneer doors. The island stayed white and plain, so the wood reads as one piece.

The laundry moved into the old kitchen space, next to the primary suite. The bath lost its tub and gained a walk-in shower with a bench.

Bedroom with a walnut bed and bench, opening to a bath with a glass shower
Primary suite, with the bath opened up behind it.

How it turned out

Tomas Ruzicka ran the site from demolition to the final punch list. The family moved into the new kitchen in week 19, before the old one came out.

The final cost came in 3 percent over the signed price, all of it from two change orders the owners asked for: a deck one step wider and a heated bathroom floor.

Planning something like this in Western Springs or nearby

Send the town, the rooms and a budget range. Johanna will tell you which service fits and what the fee would be.

Johanna reads every inquiry herself and replies soon, usually with two or three questions and a time to talk.